Discussed progress done towards finalizing the project commitment.
Notes:
Showed the Horizon policies plugin to HoD.
Discussed uncertainty surrounding whether to have the plugin use its own dashboard group or just preside underneath one of the existing groups.
Plugin is currently just a skeleton template with an Angularjs front-end and a python back end.
Discussed the backlog.
No new stories have been added to it.
New additions or modifications will be discussed in team meeting 6th March.
Discussed deadlines.
The plugin is the deliverable
The commitment is negotiable and could be modified if there is a necessity to do so.
Discussed team dynamics.
Has absence of certain team members due to sick leave affected the team as a whole or its progress.
Discussed commitment delivery.
We might need to add an additional week to the commitment period in order to complete some research questions.
Discussed team progress.
There has been a slight delay in the timeline, approximately one week but that is due to the team prioritizing that all team members are in sync and fully up to date regarding all work that is being done.